CONSTRUCTION AND TRAFFIC BULLETIN

 

 

Coquitlam
March 13, 2015
 

Upcoming Roadworks on Lincoln Avenue

As part of Evergreen Line construction, permanent road improvements including drainage installation, paving, traffic line painting, electrical and signal work are required on Lincoln Avenue on the west side of Pinetree Way.

Work will begin the week of March 16 and continue until approximately mid-April. Paving requires warm, dry weather conditions, so this work is weather dependent and the schedule is subject to change.

WHAT TO EXPECT

Crews will be working Monday to Saturday from 7 a.m. to 5 p.m. with intermittent nighttime work as required for approximately one month. The majority of work will take place during the day, however, when full closure of Lincoln Avenue is required, work will take place at night.

  • Lincoln Avenue closures will be implemented as follows:
  • Intermittent daytime lane closures of Lincoln Avenue eastbound (to Pinetree Way). Access to the mall from Pinetree Way via Lincoln Avenue will be maintained during mall business hours.
  • Full nighttime closures of Lincoln Avenue outside of mall hours. When the full closure is in effect, drivers wishing to access the mall will be detoured to Northern Avenue and/or Anson Avenue.

 

  • Intermittent lane closures of Pinetree Way southbound between Northern Avenue and Anson Avenue.
  • For approximately three days during this work, a full closure of Lincoln Avenue west of Pinetree Way will be in effect to allow crews to complete paving operations.
  • Temporary sidewalk closures will be implemented at the southwest corner of Lincoln Avenue and Pinetree Way. For the safety of all pedestrians, please follow posted signs and the instructions of traffic control personnel. The temporary detour route will be clearly marked.
  •  All traffic pattern changes will be well-signed and traffic control personnel will be on-site to assist drivers and pedestrians. Please follow the directions of traffic control personnel and posted signs while construction is underway.
  • Nearby businesses and residents can expect noise related to construction activities, including the use of heavy machinery. Every effort will be made to minimize noise and disruptions when possible.
  • To ensure the safety of transit users, southbound bus stops on Pinetree Way between Anson Avenue and Lincoln Avenue will be temporarily shifted away from active construction. Please watch for transit signs that will indicate the temporary location of bus stops.

To contact EGRT Construction, the contractor who is building the Evergreen Line, please call 604-927-2080, available 24 hours a day, 7 days a week. If you have comments or questions about the Evergreen Line Rapid Transit Project, please call the Evergreen Project Office at 604-927-4452 or email info@evergreenline.gov.bc.ca.

plain

CONSTRUCTION & TRAFFIC BULLETIN: Disassembly of the Launching Truss on Pinetree Way

CONSTRUCTION AND TRAFFIC BULLETIN
Coquitlam
February 27, 2015

 

Disassembly of the Launching Truss on Pinetree Way

Starting the week of March 2 Evergreen Line construction crews will begin to dismantle the launching truss (the large yellow and blue steel structure that has been used to build the elevated guideway) on the west side of Pinetree Way just south of Guilford Way. 

In order to complete the work as quickly as possible and to minimize traffic disruption, crews will be working 24 hours a day to dismantle the launching truss. This work will take approximately one month complete.

WHAT TO EXPECT

  • While this work is underway, northbound lane closures on Pinetree Way between Glen Drive and Guildford Way will be in effect 24 hours a day, seven days a week. When lane closures are in effect, please watch for construction signs, drive with caution and follow the directions of traffic control personnel.
  • Intermittent stoppages of two to three minutes for northbound traffic on Pinetree Way for large delivery trucks to enter and exit the work site. Traffic control personnel will be on-site to direct drivers.
  • To minimize traffic disruption, transport of large components of the disassembled launching truss from Pinetree Way may occur at night however, the majority of the work will be done during the day.
  • Noise related to the use of heavy machinery should be expected as part of this work.
  • Every effort will be made to complete nosier activities earlier in the evening to minimize disruptions. Crews will minimize the use of back-up beepers, including using traffic control personnel at night to assist with the maneuvering of trucks. However, back-up beepers are required for safety.
  • When crews are working at night, construction lighting will be used and efforts will be made to angle the lighting away from nearby residents.
  • Temporary parking restrictions on the east side of Pinetree Way between Glen Drive and Guildford Way will be in effect. Please watch for signs indicating the dates and times when parking restrictions are in place.
  • For the safety of all pedestrians in the area, please follow the directions of traffic control personnel and posted signs while construction is underway.

To contact EGRT Construction, the contractor who is building the Evergreen Line, please call 604-927-2080, available 24 hours a day, seven days a week. If you have comments or questions about the Evergreen Line, please call the Evergreen Line Project Office at 604-927-4452 or email info@evergreenline.gov.bc.ca.

plain

CONSTRUCTION AND TRAFFIC BULLETIN

 

 

Coquitlam
February 12, 2015. 

Construction of Elevated Guideway over Glen Drive
Construction of the elevated guideway on the east side of Pinetree Way is progressing. During the week of February 16, crews will be nearing Glen Drive and will begin the process of lifting the guideway segments into place over the roadway. As part of this work there will be temporary lane closures on Pinetree Way and on Glen Drive for up to two weeks.

WHAT TO EXPECT 

  • Lane closures of Pinetree Way northbound between Obelisk Way and Glen Drive. Crews will be working Monday to Saturday, 24 hours a day, however, the majority of the work at this location will be done during the day.
  • Traffic pattern changes on Glen Drive will be implemented as follows:
    • Intermittent daytime lane closures of Glen Drive on the east side of Pinetree Way. 
    • The right-turn from Pinetree Way northbound to Glen Drive eastbound will be restricted while this work is underway. Drivers will be detoured further north to Guildford Way and Westwood Street. 
  • Intermittent stoppages of two to three minutes for traffic on Glen Drive while crews use the launching truss to move guideway segments into place over the roadway. If a full closure of Glen Drive is required, residents will be notified.
  • Temporary sidewalk closures will be implemented on the east side of Pinetree Way between Glen Drive and Obelisk Way and at the south east corner of the intersection of Pinetree Way and Glen Drive. For the safety of all pedestrians, please follow posted signs while construction is underway. The temporary detour route will be clearly marked.
  • Nearby businesses and residents can expect noise related to construction activities, including the use of heavy machinery. Every effort will be made to minimize noise and disruptions when possible.
  • Access to residents’ homes and businesses will be maintained. Business access signs will be installed so that the entrances to businesses are clearly marked.
  • All traffic pattern changes will be well-signed and traffic control personnel will be on-site to assist drivers and pedestrians. Please follow the directions of traffic control personnel and posted signs while construction is underway.

Once the section of guideway that spans over Glen Drive is complete, the launching truss will continue on the east side of Pinetree Way north to the future Lafarge Lake-Douglas Station. Elevated guideway construction will be complete in March 2015.

To contact EGRT Construction, the contractor who is building the Evergreen Line, please call 604-927-2080, available 24 hours a day, seven days a week. If you have comments or questions about the Evergreen Line, please call the Evergreen Line Project Office at 604-927-4452 or email info@evergreenline.gov.bc.ca

 

plain

CONSTRUCTION AND TRAFFIC BULLETIN: Northern Avenue

 

Coquitlam
January 27, 2015

 

Construction of the Elevated Guideway over Northern Avenue
 

As part of elevated guideway construction for the Evergreen Line, there will be temporary lane closures on Pinetree Way and on Northern Avenue starting the week of February 2. Lane closures in this area will continue for up to two weeks to allow crews to lift guideway segments into place over Northern Avenue and on the eastside of Pinetree Way between Obelisk Way and Glen Drive using the launching truss.
 
WHAT TO EXPECT 

  • Lane closures of Pinetree Way southbound and northbound between Northern Avenue and Glen Drive. Crews will be working Monday to Saturday, 24 hours a day. 
  • Northern Avenue closures will be implemented as follows:
    • Intermittent daytime lane closures of Northern Avenue westbound (from Pinetree Way). Drivers will be not be permitted to turn right on Northern Avenue from Pinetree Way southbound when the closures are in effect. Access to the mall from Pinetree Way via Lincoln Avenue will be maintained during mall business hours. 
    • Full nighttime closures of Northern Avenue outside of mall hours. When the full closure is in effect, drivers wishing to access the mall can use Lincoln Avenue. 
  • Intermittent stoppages of two to three minutes for traffic on Northern Avenue while crews use the launching truss to move guideway segments into place over the roadway. 
  • Temporary sidewalk closures will be implemented on the west side of Pinetree Way at Northern Avenue. For the safety of all pedestrians, please follow posted signs while construction is underway. The temporary detour route will be clearly marked.
  • Nearby businesses and residents can expect noise related to construction activities, including the use of heavy machinery. Every effort will be made to minimize noise and disruptions when possible.
  • Access to businesses will be maintained. Business access signs will be installed so that the entrances to businesses are clearly marked. 
  • All traffic pattern changes will be well-signed and traffic control personnel will be on-site to assist drivers and pedestrians. Please follow the directions of traffic control personnel and posted signs while construction is underway.

Once the section of guideway that spans over Northern Avenue is complete, the launching truss will be lifted over the existing structure in the middle of the roadway and construction of the elevated guideway will continue on the east side of Pinetree Way north to the future Lafarge Lake-Douglas Station. Elevated guideway construction will be complete in March 2015. 

To contact EGRT Construction, the contractor who is building the Evergreen Line, please call 604-927-2080, available 24 hours a day, 7 days a week. If you have comments or questions about the Evergreen Line, please call the Evergreen Line Project Office at (604) 927-4452 or email info@evergreenline.gov.bc.ca.

plain

CONSTRUCTION AND TRAFFIC BULLETIN

 

Coquitlam
UPDATED
January 23, 2015
Ongoing Nighttime Utility Relocation Work
On Pinetree Way near Lincoln Avenue

As part of construction of the Evergreen Line, intermittent nighttime utility relocation work within the Coquitlam Centre parking lot and on Pinetree Way between Lincoln Avenue and Barnet Highway will continue until early February 2015.

WHAT TO EXPECT
• This work will take place at night from 10 p.m. to 6 a.m. Nighttime work is required due to high volumes of daytime traffic on Pinetree Way.
• While this work is underway, there will be southbound lane closures on Pinetree Way just south of Lincoln Avenue.
• When lane closures are in effect, please watch for construction signs, proceed with caution and follow traffic control personnel who will assist with directing traffic.
• Nighttime noise related to saw-cutting, excavation, and the use of heavy machinery should be expected as part of this work. Every effort will be made to complete activities considered noisier earlier in the evening to minimize disruptions.
• For the safety of all pedestrians, please follow posted detour signs and instructions of traffic control personnel.

To contact EGRT Construction, the contractor who is building the Evergreen Line, please call 604-927-2080, available 24 hours a day, 7 days a week. If you have comments or questions about the Evergreen Line, please call the Evergreen Line Project Office at 604-927-4452 or email info@evergreenline.gov.bc.ca.